The Union Cabinet has approved a second container terminal at Kamarajar Port in Tamil Nadu, adding two million TEUs of annual container capacity. The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, cleared the project on 25 November. It is expected to strengthen trade for the Chennai-Ennore industrial region and give southern exporters a larger gateway to global shipping routes.
Key points:
- Project cost is Rs 4,288.26 crore under the PPP model.
- The terminal will have a 900-metre berth and 18-metre draft.
- Capacity will come in phases of 1.1 million and 0.9 million TEUs.
- The port will separately spend about Rs 450 crore on dredging.
What Has Been Approved
The terminal will be built at Kamarajar Port Limited, formerly Ennore Port Limited, on Tamil Nadu’s east coast. A private concessionaire will design, build, finance and operate it under a 40-year concession, including 48 months of construction, and then transfer it back. The berth will be 900 metres long and 30 metres wide. With an 18-metre draft, the port will be able to receive large container vessels of up to 24,346 TEUs and 400 metres in length. Direct calls by bigger ships can reduce reliance on foreign hub ports and lower extra handling costs for exporters.
Why More Capacity Is Needed
The existing container terminal has 0.8 million TEUs of annual capacity and handled around 0.7 million TEUs in 2025-26, or about 88 per cent use. The port handled 49.08 million tonnes of cargo and more than a thousand vessels that year. Its container traffic has grown at close to 9.9 per cent a year over five years, faster than India’s roughly 7 per cent. The new terminal will serve automobiles, auto components, engineering goods, electronics and chemicals from Tamil Nadu and nearby states. See also our reports on the construction equipment scheme and the Silchar airport approval.
Timeline and Jobs
Phase I will add 1.1 million TEUs within 24 months of the concession award, with operations from the 25th month. Phase II will be built between the 25th and 48th months and add 0.9 million TEUs, with full operations from the 49th month. The concessionaire will be chosen through open global bidding and recover its investment through user charges, so the Centre has no direct financial liability. The project is expected to support about 750 jobs during construction and 800 during operations. More details are in the original report.
Frequently Asked Questions
Where is Kamarajar Port? It is near Chennai on Tamil Nadu’s east coast.
How much capacity will be added? Two million TEUs a year in two phases.
Who funds the project? A private concessionaire funds it under PPP.